Clacton-on-Sea

Wed 24 Oct

Our resident King Post Wall expert Paul Newman is working for Aarsleff Sheet Piling in Clacton on a bank stabilisation scheme utilising 254 x 254 x 89kg H-Beams @8mts installed conventionally using an 80t Kobelco Crawler Crane and a 15HFV Vibro. Piling Personnel Ltd are providing Supervision and Welders for the project.


Aberdeen Harbour

Wed 24 Oct

Works are now completed for Southbay Civil Engineering at Aberdeen Harbour Replacement Debris Screen. Piling Personnel Limited have provided Supervision, Piling Operatives and Welders for this contact. Works had to be completed before the Salmon started their run up river and that is exactly what was achieved, working long hours and seven days a week, works were completed on time. Well done to all.


Buckie Harbour North Pier Refacing Works

Fri 31 Aug

Works are now completed at Buckie Harbour on the Moray Firth Coast where Piling Personnel Ltd have been working for Southbay Civil Engineering Ltd on the Buckie Harbour North Pier Refacing Works.